Planning permission - how long does it take
Local planning authorities are expected to make a decision on planning applications as quickly as possible.
The statutory determination period for validated planning applications, which local planning authorities should not exceed, is 8 weeks for straight-forward planning applications, 13 weeks for unusually large or complex applications, and 16 weeks if the application is subject to an Environmental Impact Assessment (EIA).
The determination period can be extended further by agreement in writing with the applicant.
If the determination period is exceeded without agreement, the applicant can appeal to the Secretary of State, although this in itself can take some time.
Where an extension has not been agreed, the Government’s ‘planning guarantee’ commits that no application should take more than a year, including any appeal. In practice this means the applications itself should be decided in no more than 26 weeks, allowing a further 26 weeks for any appeal.
Where an extension has not been agreed, the applicant does not appeal, and the application remains undetermined after 26 weeks, the planning fee will be refunded to the applicant.
The Growth and Infrastructure Act 2013 gives the Secretary of State power to 'designate' local planning authorities if their performance in handling major planning applications is below an acceptable standard. Local planning authorities under special measures have applications determined by the planning inspectorate and lose a proportion of the application fee. Special measures designation is reviewed annually to allow improving authorities to regain their determination powers.
Delays can be caused by incomplete applications, applications that are not in an appropriate form, payment of fees, the timing of planning committee meetings, and so on. To ensure that there are no such delays, it is wise to seek pre-application advice from the local planning authority who can clarify the form of the application required and the information expected. If it is necessary for the application to be determined by the local planning committee (rather than by planning officers under delegated authority), they will be able to advise about the timing of meetings and whether the applicant might make representations to the committee.
Planning performance agreements can be prepared for complex applications, or applications where the statutory timescale is likely to be exceeded. These are voluntary undertakings that enable local planning authorities and applicants for planning permission to agree the timescales, actions and resources necessary to process a planning application. They are not intended to be legally-binding contracts, but are in the spirit of a ‘memorandum of understanding’.
The government publishes development control statistics which provide historical data about how long local authorities take to make a decision once a planning application has been submitted.
See also: How long does planning permission last.
[edit] Related articles on Designing Buildings
- Approval of conditions on a planning permission.
- Avoiding planning permission pitfalls.
- Environmental Impact assessment.
- Growth and Infrastructure Act.
- Hope value.
- How long does planning permission last.
- Local planning authority.
- Planning appeal.
- Planning appeal.
- Planning guarantee.
- Planning performance agreement.
- Planning permission.
- Pre-application advice.
- Special measures designation for under-performing planning authorities.
- The difference between planning permission building regulations approval.
- What is a housing start?
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
Comments